Congo – Pipeline construction between Kouakouala and Djeno
Congo - Construction of a 28.7km 12” diameter pipeline between the Kouakouala extraction site and Djeno
This integrated contract for Zetah Congo, implemented in 2002, includes engineering, equipment supply, construction and installation (EPCI).
ETE carried out the upstream studies, provided all procurement services (purchasing, logistics, delivery to site), supervised the work and provided technical assistance for start-up (selection of service providers, team coordination, work on the client’s premises, tests and commissioning).
The project was completed in 8 months.